October 24, 2018 - Roland Chong

Comments are off for this post.

The new dental build has stalled in weeks 21 and 22!

Yes we have not moved much since the last 2 weeks! Ducon building solutions have completed all their works but due to the lethargy of the electricity companies, retailer and distributor alike, we are sitting on our hands.

The building is looking very nice but we cannot move in as yet. We needed to wait for the electricity to be disconnected for the demolition of the old surgery to happen. We have been pushing hard to have this happen……..

And then at the last minute we actually received confirmation of the day for disconnection! At the end of week 22 we were informed by Ausnet they would disconnect our electricity. And here we are……

Finally the disconnection happened! It only took them 3 hours and the whole process was completed. All that pain with dealing with them and Lumo energy for 3 hours of work! What a joke! Cannot understand why it takes so long for something as simple as this to happen.

Now we wait again for Maroondah council to process our demolition request and we are ready to demolish! I hope the council is more organised than the services. But then again nothing surprises me anymore.

I hope to have better news next week everyone. In the meantime it is business as usual at ProCare Family Dental. Please contact us for appointments our receptionist will organize times for you and your family.

Roland Chong

Roland has over 18 years experience as a general dentist. Roland does all aspects of general dentistry with a special interest in prosthodontics (crown and bridge work) and cosmetic dentistry. A member of the International Team of Implantology, Roland is constantly developing his skills by collaborating with international experts.